| In
the fall of 2005, 58-member Wake Radiology found itself
feeling vulnerable. Having achieved the holy grail of
the electronic practice by banishing paper and film,
the practice understood that it had much to lose if
it lost the network over which it leveraged subspecialized
reads across three area hospitals and 11 standalone
imaging centers in North Carolina’s Triangle area:
Raleigh, Durham, Chapel Hill, and Research Triangle
Park.
Even the telephones were running over
the network via voice-over IP (VoIP). So Wake elected
to tighten up its IT practices by building a Tier 2+
Data Center.
“People
need to understand the cost of down time, of not having
a system. An organization like ours runs on electrons.
It’s like blood.”
—Ronald
B. Mitchell, MSc, CIO, Wake Radiology
Any interruption in effect takes the
business down, and not every practice is that way,”
Mitchell continued. “Some are still passing paper
and some are still printing film. Each individual practice
needs to decide for itself the cost of systems and network
failure, and really go through different scenarios and
try and figure out for them what the cost is, and then
decide what they want to spend to avoid that cost.”
There were no precipitating events
that convinced the practice to make its move. In fact,
the equipment and existing network were fairly reliable.
Nor did Mitchell provide the partners with a hard and
fast dollar figure for a network failure. “A lot
of the risk was assessed in soft dollars, relationships
with patients and referring physicians mean a lot to
us, and patient care is paramount,” he explained.
“All of those would be affected if there was an
extensive network outage.”
In considering that downtime could
be extensive and the resulting cost quite high, Wake
Radiology gave the go-ahead to build a data center where
a parking lot formerly lay. They broke ground in the
spring of 2006, and in January 2007 began moving into
the new 1,140-sq-ft data center housed in an addition
to its Raleigh-based administration building. Mitchell
estimates they have enough storage space to meet the
needs of the practice for 15 years and is actively seeking
tenants to generate some revenue through the IT arm
of the practice.
What Is a Tier II+ Data Center?
Mitchell, who joined the practice in October 2005, believes
the previous data center did not even meet the criteria
of a Tier I data center. “The original location
was two converted offices, and they did not have a raised
floor and the air conditioning was unreliable,”
Mitchell explained. “I did put a monitor in the
room and if my alarm went off in the middle of the night—and
it did—I had about half an hour to get down there
and do something about it before the machines shut down
due to overheating. I was pretty happy to not have to
do that anymore.”
Wake hired a consulting company to
provide guidance in building the center, Chicago-based
Forsythe. A Tier II data center is composed of a single
path for power and cooling distribution, with redundant
components, and is considered slightly less susceptible
to disruptions from planned and unplanned activity than
a Tier I. Other features include a raised floor, a UPS
(uninterruptible power supply), and engine generators.
Maintenance of the single path and other parts of the
site infrastructure will require a processing shut down,
providing 99.741% availability. The
tier classification system includes four tiers, and
a white paper from The Uptime Institute, Santa Fe, NM,
provides further details on IT industry standard classifications
for tier performance in data centers (pdf).
The data center Wake built is actually
closer to a Tier III, as it features dual power and
cooling paths. “The first thing to remember is
that those classifications really represent gradations,”
Mitchell explained. “We really are more than a
Tier II in that we do have redundancy for most of our
system, in power, network and air conditioning. And
in the fire alarm system we have two different VESDA
(very early smoke detection apparatus) systems. So it’s
extensive redundancy, and it has proven to be very useful
and has kept the data center up. We have not had downtime…and
we have had failures, but they are failures we can predict
and failures for which redundant components pick up
and continue. So it’s working for us.”
In North Carolina, power failures
are common due to frequent thunderstorms, but the UPS
systems pick up, and the generator picks up after that.
Mitchell also had a failure in an in-cabinet power distribution
unit (PDU), which he describes as a glorified power
strip with intelligence. But the duplicate PDU inside
the cabinet carried on and enabled the servers to continue
running.
“All of our servers have dual
power supplies,” Mitchell said. “Inside
the cabinet you will see a plug coming out of the server
on one side and plugging into a power distribution unit.
Then on the other side, there’s another one that
comes off the other UPS. It does provide the redundancy
we need. We have had networking outages at our remote
locations and the users haven’t even known about
them because the redundant connection picked up and
continued to provide images and clinical data.”
And if an air conditioner fails, Mitchell
will not be roused in the middle of the night to turn
fans on the servers: a second unit will kick into action.
Design Features of the Wake
Data Center
While the data center was being built, Mitchell visited
the site daily to be sure the center was built to specifications.
Mitchell provided the following descriptions
and accompanying images of key design features:
Location. The data
center was placed on the inside of the building with
no part open to an exterior wall. The sub-floor is on
slab, and there is nothing above the center, including
no equipment on the roof.

Flooring. The center
was built on a 2-ft raised floor throughout. In actuality,
the raised floor is at the same level as the rest of
the addition, but the sub floor was sunk 2 feet. The
sub floor is graded to channel any water that might
collect there to a drain. All pipes and cables run under
the floor, including power and data in separate troughs.
The raised floor tiles are concrete-filled.
Air Conditioning.
Two 15-ton Liebert CRAC (computer room air conditioners)
units push cold air down under the raised floor and
up through perforated tiles into the equipment. Either
unit could handle the full load of the data center equipment,
but the redundancy provides for unit failure or planned
outage due to maintenance.
Raised flooring
showing equipment rows
Layout. The data
center layout allows for four rows of equipment cabinets
(two rows are currently in use). Each row of equipment
faces in opposite directions so that the aisle between
the first and second rows is called a hot aisle since
the backs of the cabinets face each other and the aisle
between the second and third rows is a cold aisle since
the fronts of the cabinets face each other.
Power. The first two
cabinets in each row consist of an APC Symmetra 40Kw
UPS and associated PDU (power distribution unit). Each
UPS/PDU receives a 480 Volt supply from the utility,
regulates and smooths it, and provides power to the
cabinets in the row for both 120V and 208V outlets as
needed. In addition, each UPS also supplies power to
the cabinets in the adjacent row. Since nearly all the
servers and other equipment in the cabinets have dual
power supplies and receptacles, this arrangement provides
power redundancy should any of the UPS units fail or
need to be taken out of service for maintenance.
For utility blackouts, the UPS can
handle the load for about 20 minutes. However, after
less than 30 seconds of utility power failure, a 350Kw
generator housed behind the building automatically engages.
The generator can run for 48 hours without refueling.
Network. As with
power and air conditioning, many aspects of the network,
both inside and outside the data center, are redundant.
For example, servers with dual NICs (network interface
cards) are connected to two different switches. The
Wake data center network core consists of dual layer
III switches connected at the backplane. If one fails,
the other will keep going. For the WAN (wide area network)
connections to the imaging centers, two different companies
are used and each one's connection comes into the building
from two different streets, thus eliminating the effects
of the “backhoe through the cable” problem.

Monitoring. An APC
Infrastruxure Manager provides environmental monitoring
of the power, including the UPS/PDU cabinets as well
as the power distribution units in each server cabinet,
the temperature and humidity, door opening, air movement
and motion. In addition, the system monitors for any
water build-up on the sub-floor. For any critical problems,
emails and pagers are used to notify appropriate IT
personnel.
The monitoring system has also been
extended to network closets in the imaging centers,
where UPS units powering critical network equipment
report back to the environment monitor a number of parameters,
including time on battery due to power failures, battery
health, self-test results, and closet temperature and
humidity.
Critical aspects of each server are
also monitored, as well as overall network performance
with two additional systems. The tools enable IT to
pre-empt potentially critical issues and speedily locate
network components that are causing problems.
Fire control. A three-hour fire-rated
wall surrounds the entire data center and separates
it from the offices outside that are protected by a
sprinkler system. Inside the data center, a very sophisticated
early warning system, a VESDA (very early smoke detection
apparatus) uses a series of porous pipes in the room,
under the floor, and over the drop ceiling to constantly
sniff the air for particulate matter. The VESDA units
have a number of levels for reporting smoke.
The fire suppression system in the
data center is a dry-pipe sprinkler system. With this
solution, the pipes above the data center ceiling do
not have any water in them until there is a fire. If
that happens water sprinkling is limited to the area
of the fire.
A policy also ensures that the data
center is kept free of combustible material. Any cardboard
or paper are removed as soon as possible.
Security. The data
center has only one door for access. This is protected
by a biometric system that requires a pass-code, as
well as fingerprint recognition, and access is restricted
to a few individuals. A security camera can be viewed
remotely and graphical displays of movement and door
opening activity can also be viewed. Entrance to the
surrounding office space is restricted by pass-code
and an alarm is set, including movement alarms, when
the building is not occupied.
Backups & Replication.
All the images are stored on servers in the
data center. In addition, they are replicated to a storage
system at one of our imaging centers. Database backups
are done daily via a robotic tape library, and the tapes
are taken to a secure location, off site.
Current and Future Needs
Wake Radiology is currently producing and archiving
approximately 4 terabytes of data a year, and all of
those images are kept online, all of the time. “We
don’t have a hierarchical system as some practices
and some hospitals do,” Mitchell explained. “I
think that’s a great decision, because I have
been in situations where there is a hierarchy, and it’s
a problem because you really never can predict what
it is the radiologist wants to see. And if they have
to wait, obviously that is not good.”
The data center currently contains
about 20 terabytes, and it is only using two of four
available rows in the data center. “There is room
in the data center for another two rows, so from a data
center perspective, we are ready to expand as needed,”
Mitchell said.
Mitchell also is actively shopping
the space to potential tenants. “One of the things
we can and are looking at is offering space in the computer
room to other organizations that need perhaps a backup
data center or some place to store images,” he
said. “This center is a great environment for
a server, no matter whose server it is.”
|